30–240 kW DC Fast Charging Equipment

Evaluate 30 kW, 60 kW, 120 kW and 240 kW DC charging classes for sites with different dwell times. Nameplate power is not guaranteed power delivered to a specific vehicle.

Design decision

For DC charging, delivered power is voltage × current. An illustrative 400 V vehicle drawing 200 A receives about 80 kW before cable losses, even at a charger advertised in a higher power class. The vehicle’s battery-management request, state of charge, temperature and the charger’s voltage-current envelope all affect a session. Compare a time-based charging curve across representative vehicles, rather than dividing battery capacity by nameplate power.

When this approach fits · Limits and alternatives

Shared outlets may divide a cabinet’s available power. Require a simultaneous-session test with different vehicle voltages and request the behavior when a module or backend connection fails. A CCS2 connector does not by itself prove vehicle interoperability, payment readiness, legal metering or backend compatibility. For low utilization and long stays, assess a smaller power class against connection cost before specifying a larger unit.

Procurement checks

  • Verify CCS2 pinout and the real output voltage-current curve
  • Require testing for power sharing and thermal derating
  • Check metering, backend integration and conformity for the exact EU model

Evidence to request

Define the installation country, supply, arrival and departure times, energy per session and operating constraints. Ask for an electrical design, exact configuration, test evidence and acceptance plan. Include support responsibilities and data ownership in the written scope.

Evidence to request

An original procurement guide using general engineering principles and public standards context. Links explain the subject; they do not certify any equipment.

Discuss a project

Define the installation country, supply, arrival and departure times, energy per session and operating constraints. Ask for an electrical design, exact configuration, test evidence and acceptance plan. Include support responsibilities and data ownership in the written scope.

Discuss a project →

← EV charging equipment & project solutions

We do not currently use optional analytics, advertising or tracking cookies. Essential website functions and protective hosting mechanisms may operate where permitted.

Strictly necessary
Required when used
Analytics
Not installed or active
Advertising / marketing
Not installed or active

If optional tracking is introduced later, it must remain disabled until any required consent is obtained.

Privacy Notice